tellijale nõuetekohase arvutimängu arendamine
Dates
Start 1/7/26, 8:00 AM Finish 1/16/26, 9:00 AM
Baseline Start Baseline Finish
Actual Start Actual Finish
Duration
Scheduled 7.125 days Remaining 7.125 days
Baseline 0 days Actual 0 days
Percent Complete 0%
Work
Scheduled 107 hours Remaining 107 hours
Baseline 0 hours Actual 0 hours
Costs
Scheduled $3156.00 Remaining $3156.00
Baseline $0.00 Actual $0.00
Variance $0.00
Notes